Tuesday, October 19, 2010

Due Care, Continuing Obligations and the CERCLA landowner defenses

There have been alot of  ASTM standards issued the past few years but one of the more important ones will likely be the Continuing Obligations practice that is currently in draft form. It is important because it is critical for landowners to maintain their liability protection after they take title.

It is important for consultants, attorneys and landowners to realize that the landowner liability protections are affirmative defenses-that means the person seeking to assert the defense has the burden of proving that they qualify for the liability protection. I suspect the caselaw under the third party defense and innocent landowner defenses will serve as an example of how courts are going to interpret the scope of the reasonable steps/continuing obligations obligations. If so, the courts will narrow construe the defenses-in other words make it hard for parties to establish that they are not liable.

The decisions in U.S. v. Honeywell, 2008 U.S. Dist. LEXIS 13432  (C.D. Ca. 2/22/08) and the 2006 AMCAL v. Pacific Clay,  457 F.Supp.2d 1016. (E.D.Ca. 2006) illustrate that there is plenty of liability remaining out there for purchasers of contaminated property who move around contaminated soil. I think we would do a disservice to clients if potential users of the practice if we suggest that all they need to do is erect a fence or notify the authorities.

It should also be pointed out that some jurisdictions still hold that passive migration is disposal though a majority of courts that holds passive migration is not a release. Landowners in jurisdictions where mere migration is disposal will probably have to implement more rigorous actions to satisfy 'reasonable steps' (i.e. Stop ongoing releases) than those in jurisdictions following the majority rule.

Thus, landowners need to be very careful not to inadvertantly forfeit their liability after they take title. Obviously, the determination of what steps are 'reasonable' will be site-specific. However, we can probably make some general observations.

As part of the reasonable steps obligations, landowners have to stop continuing releases, prevent any threatened future releases and prevent or limit exposure to releases of hazardous substances. It would seem from any reading of the legislative language, history and the 1995 EPA Guidance on Contaminated Aquifers that a BFPP, ILO or CPO do not have to remediate groundwater. On the other end of the spectrum, it is also probably clear that simply erecting a fence or notifying the authorities is probably not going to satisfy the reasonable steps requirement in most cases.
   
The big question is what does such a party have to do about contaminated soil? I think it is fair to suggest that they would also not have to engage in long-term remedial measures such as would have to be implemented as part of a RI/FS. It would seem to me that landowners seeking certainty about whether they have implemented 'reasonable steps' should probably anticipate that they will have to perform the equivalent of removal actions or interim remedial measures such as removal of USTs, excavation of grossly contaminated soils and probably installation of vapor mitigation systems. I think source removal and eliminating the exposure pathway should be the admission price for liability relief